West Bloomfield Township will open construction bids Thursday, Oct. 22, for improvements to Karner Farms Dog Park.
The federally funded project will replace the park's gravel parking lot with paved surfaces and add walkways, fencing and other accessibility improvements.
Sealed bids are due by 2 p.m. at the Township Clerk's office in Town Hall, 4550 Walnut Lake Road, according to the township's bid documents.
Construction is scheduled to begin Aug. 2, 2027, and finish Oct. 29, 2027.
The township issued an addendum Oct. 20 to correct the bid-opening weekday from Wednesday to Thursday. The deadline remains 2 p.m. Oct. 22.
The addendum also updates several construction specifications and requires bidders to submit a signed copy with their proposals.
Plans call for removing the existing gravel parking lot, installing chain-link and woven-wire fencing, and adding pavement markings and detectable warning surfaces.
The township is also seeking alternate bids for additional paving in the north section of the parking lot and utility work involving DTE.
The project uses federal Community Development Block Grant funding. Contractors must follow applicable federal requirements, including prevailing-wage rules under the Davis-Bacon Act.
The township plans to award the contract to the lowest responsible bidder. Proposals must include bid security equal to 5% of the bid amount.