The West Bloomfield Parks and Recreation Commission is scheduled to vote Wednesday, Nov. 18, on its proposed 2027 budget, which includes $2,796,000 in requested capital spending.

The commission will consider approval of the 2027 General Appropriations Act Resolution and receive a three-year budget comparison covering 2025 through 2027, according to its Nov. 18 meeting agenda.

Commissioners will also review changes to the Connect Community Center construction project and discuss the township's next five-year parks master plan.

Capital request totals $2.796 million

Executive Director Kelly Hyer presented the draft 2027 budget during the commission's Oct. 7 special workshop.

Hyer attributed most of the projected increase in expenditures to cost-of-living adjustments, inflation and higher employee health care costs, according to the approved workshop minutes.

The department also expects lower revenue because of reduced program space following the Recreation Activities Center closure, paving projects and changes to class offerings.

Some capital projects originally planned for 2026 will carry into 2027, alongside new projects addressing maintenance needs.

Parks Superintendent Chris Frey reviewed the proposed projects, their funding requirements, schedules and priorities during the workshop.

The total capital request for 2027 is $2,796,000. That figure represents the proposed capital component of the budget, not the department's total annual spending.

The commission reviewed the budget in October, with the workshop minutes identifying Nov. 18 as the anticipated adoption date.

Those minutes also identified Dec. 7 as the date for the Township Board's consideration of the budget.

Connect Community Center change orders

Commissioners are scheduled to receive six change orders involving Frank Rewold & Sons, the contractor for the Connect Community Center bond project.

Two of the changes carry additional costs drawn from contingency funds held by the project owner.

Change Order 009 totals $41,185.51 for design revisions, including structural steel resizing, HVAC zone control changes, structural masonry modifications and additional brick control joints.

Change Order 014 adds $5,186 for excavation and concrete work, offset in part by reduced steel requirements at elevator openings.

The other four change orders have no net additional cost. They involve adjustments to paving subbases and drainage, roofing and siding work, skylights, and building material specifications.

The commission previously approved a total Connect Community Center project budget of $28,378,917 at its May 27 meeting.

That project budget is funded through bond proceeds and contributions from the Parks and Recreation fund balance.

Wednesday's consent agenda also includes an October construction payment of $322,151.08 to Frank Rewold & Sons.

The payment is part of an invoice journal totaling $681,600.49.

Health insurance and master plan

The commission will consider a resolution to opt out of requirements under Michigan Public Act 152, which governs publicly funded employee health insurance contributions.

At the October workshop, Hyer discussed insurance coverage for 24 full-time employees enrolled in the department's health plan.

According to the minutes, employees currently make no enrollment contribution. Workshop participants reached a consensus to defer changes to employee contributions or insurance plans until 2028.

Commissioners will also receive a presentation on the draft 2027–2031 Parks and Recreation Master Plan.

The commission approved a professional services agreement with livingLAB in July to prepare the five-year plan at a cost not exceeding $45,550, according to the approved July meeting minutes.

The plan is intended to guide future parks, recreation programs, facilities and capital investment priorities.

Wednesday's agenda lists the master plan for presentation and discussion, not final adoption.

Other business includes a discussion of a commission vacancy, an updated capital asset management policy and amendments to the 2026 budget.

Meeting information

The West Bloomfield Parks and Recreation Commission meets at 6 p.m. Wednesday, Nov. 18, at the Connect Senior Center, 33230 W. 14 Mile Road, West Bloomfield.

The agenda includes two public-comment opportunities, including a forum limited to two minutes per speaker.

Residents who need accessibility accommodations may contact Kahlia Chehade at 248-451-1918. The commission requests advance notice to allow time to arrange assistance.

Residents can review meeting documents and the proposed 2027 budget through the West Bloomfield Parks Commission webpage.

The proposed budget and other scheduled actions remain subject to commission consideration at Wednesday's meeting.