West Bloomfield Township Public Library trustees will review a proposed $7.99 million operating budget Wednesday, Nov. 11, alongside plans to replace the Westacres Branch roof and strengthen the library's artificial intelligence policies.

The spending proposal for fiscal year 2027–28 balances $7,991,100 in projected revenue against the same amount in operating expenses.

According to the library's November board meeting packet, trustees will receive the budget presentation during their 6:30 p.m. meeting at the Main Library, 4600 Walnut Lake Road.

The board is not scheduled to adopt the budget Wednesday. Instead, trustees are expected to set a public hearing for Dec. 9.

Personnel costs rise as materials funding grows

Executive Library Director Cathy Russ, Associate Library Director Jeff Crocker and Finance and Human Resources Manager Hillary LaBonte outlined the proposed budget in a Nov. 4 memorandum.

Projected operating revenue is $44,645 below the current fiscal year's revenue estimate, primarily because of conservative assumptions about interest earnings and donations.

The library expects to revise its property tax revenue estimate after receiving updated 2027 tax information.

On the expense side, medical insurance premiums are increasing 18% beginning Dec. 1. The budget also incorporates a standard 3% employee wage increase scheduled for April 2027.

Utility expenses are projected to rise $8,000 to $272,000, partly because of higher water and sewer rates.

The library proposes increasing its materials budget by $127,335, emphasizing eBooks, eAudiobooks and lending kits.

That would raise materials spending from 19.58% to 20.35% of the operating budget, bringing it back within the library's policy target of 20% to 25%.

Westacres roof replacement moves toward bidding

The board will also consider bid specifications for improvements at the Westacres Branch, 7321 Commerce Road.

The branch's roof is approximately 25 years old. A 2025 assessment by Roofing Technology Associates found it at or near the end of its useful life.

Proposed work includes replacing the roof and gutters, repairing vinyl siding and resealing windows and doors.

Optional improvements include automatic entrance doors, accessible bathroom doors, exterior brick staining and a new sign along Commerce Road.

Under the proposed schedule, contractors would submit bids by Dec. 2, with a recommendation expected at the board's Jan. 13, 2027, meeting.

Construction could take place from early spring through early summer 2027.

The library proposes spending $726,939 on capital improvements during fiscal 2027–28, including the Westacres project, technology replacements and HVAC improvements at the Main Library.

The spending plan would leave approximately $3.69 million in the Capital Improvement and Automation Development Fund.

The proposed annual contribution to that fund is $221,475, below the $491,032 identified as necessary to support the library's long-term capital plan. Library staff anticipate increasing the contribution during the fiscal year.

AI policy revisions emphasize privacy

Trustees will also consider changes to Library Policy No. 42, which governs artificial intelligence use.

The policy was first adopted in December 2025.

The proposed revisions would strengthen privacy requirements for employees and library patrons, establish additional staff training expectations and clarify how violations are handled.

The revised language would prohibit employees from entering personally identifiable information into AI tools.

It would also prohibit AI-generated synthetic media in library programming, services and marketing.

The changes remain proposals until approved by the board.

Budget hearing expected in December

The library's official board schedule confirms the Nov. 11 and Dec. 9 meetings, both at 6:30 p.m. in the Main Library Conference Room.

Trustees are expected to establish Dec. 9 as the public hearing date for the fiscal 2027–28 operating and capital budgets.

Residents can review board materials through the library's website or request copies at the Main Library and Westacres Branch.

The proposed budget, roof project and AI policy changes remain subject to board consideration.