Early December is the tentative goal for reopening the closed I-696 lanes between M-10 and I-75 in Oakland County, MDOT spokesperson Diane Cross told WDIV in its Oct. 27 report.

That reopening would not mark the end of construction. Cross said another stretch needs rebuilding in spring 2027, with work expected to continue through the end of that year.

What you need to know:

  • Before reopening: Crews still need to remove temporary pavement markings and finish other remaining tasks, Cross told WDIV. She described early December as a goal, rather than a confirmed reopening date.
  • The next stretch: Both directions between I-75 and Dequindre Road are scheduled for construction in 2027. MDOT's Restore the Reuther project information says the freeway will remain open during that work.
  • Traffic during construction: Cross told WDIV that MDOT plans to keep two lanes open during the next phase, avoiding the major detour used for the earlier work. She said the I-75 interchange had been needed for that detour, preventing crews from rebuilding the next stretch earlier.

Drivers can consult the Restore the Reuther project website for project information. MDOT urges motorists to slow down and drive safely through work zones.